Bridge Opening At 6:00 p.m. Labor Day
Date Posted : 09/03/2007

Bridge to Reopen Monday Evening

CCM News

At a press conference this afternoon, Caltrans Director Will Kempton announced that the San Francisco-Oakland Bay Bridge would be ready to open at 6:00 p.m. today, 11 hours ahead of schedule.

Praising his crews and subcontractors, C.C. Myers said it was a testimony to teamwork and thinking outside the box.

 

http://baybridgeinfo.org/Editor/assets/ldwre-op.pdf

New Bridge In Place
Date Posted : 09/03/2007

Just before 3:00 a.m. Monday, work crews moved the 6500-ton bridge into place which allows the final stages of upper and lower deck work to begin.

Caltrans closed the entire bridge at 8pm Friday night for a seismic safety repair that involves a 350-foot section of I-80 just outside the east entrance to the Yerba Buena tunnel.

The project has moved ahead of projections throughout the weekend.

*Roll in of the new replacement bridge began just before midnight Sunday, and was completed before 3:00 a.m. allowing for the finishing work to begin on the upper and lower decks of the bridge.

We will continue to update you on the progress of this project.

Use these resources for more information about this project and alternate routes:

www.baybridgeinfo.org
(510) 286 - 7167

C.C. Myers, Inc. To Begin Roll In of New Bridge
Date Posted : 09/02/2007

Demolition Completed

Rancho Cordova contractor C.C. Myers, Inc. will begin moving the new 350-foot replacement bridge on the east side of the Yerba Buena Island into place.

Demolition and debris removal of the old section of bridge, which began at 9:30 p.m. Friday night, was completed Sunday evening and the roll in of the new bridge began shortly before midnight.

C.C. Myers, Inc. began construction of the 350-ft replacement bridge January 12, 2007. Over 2700 square yards of concrete and steel were used in the structure which weighs nearly 6500 tons. The new bridge is being hoisted by eight hydraulic jacks and will be moved into position just east of the tunnel opening on Yerba Buena Island

We will continue to update you on the progress of this project.

The entire San Francisco-Oakland Bay Bridge is scheduled to be closed until: 5am Tuesday, September 4, 2007

Use these resources for more information about this project and alternate routes:

www.baybridgeinfo.org

(510) 286 - 7167