Route 80/Hercules
View images Still Image 1 Still Image 2
PROJECT LIST:
Route 205, Tracy
SFOBB Detour Tie-In Labor Day 2009
Golden Valley Road
West El Camino Bridge, Sacramento
Project I-5/50, Sacramento
Route 59, Merced River
Foothill Oaks Blvd, Shingle Springs
I-5 at State Rte 14 - Tunnel/Truck Bypass
SFOBB Roll-In Labor Day 2007
Benicia Bridge, Hwy 680/780 Interchange
Hwy. 57/60 Interchange
I-580 / 880 Emergency Repair
SR-22
Route 710
Tujunga Ave Bridge
Lozanos Rd
Route 1/Santa Cruz
Route 80/Hercules
Route 128/Geyserville
Lewis Stein Road
Napa Bridge
Santa Monica I-10 Freeway
680/24 Interchange Walnut Creek
Harbor Freeway Transit Project
City of Berkeley Overcrossing
Carquinez Bridge Approach Replacement
Lake Natoma/American River Bridge
Route 5, Sylmar


On January 19, 2006, Caltrans awarded the contract for Route 80 in Hercules to C.C. Myers, Inc. The contract work limits were the Route 80 Corridor from Route 4 to the Cummings Skyway Over-Crossing.

The contract scope widened Westbound 80 and added a new 3.1 mile high-occupancy-vehicle (HOV) lane. To accommodate a new alignment, the existing California Street Bridge was demolished and reconstructed and the Willow Street Bridge widened. Additional work included the construction of six sound walls, a soil nail retaining wall, AC resurfacing, and modifications to the traffic operation and lighting systems. C.C. Myers, Inc self-performed clearing, excavation, backfill, PCC paving, and all bridge and structure work.

Work began in April 2006 with completion in October 2006. The major challenge was a 130 working days completion.